PROJECT UPDATES

Metro Project Updates

Construction Schedule (Updated on: 15-July-2017)

Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

Projects Updates

STAGEWISE DETAILS

Stage TOTAL KMS TOTAL PIERS TOTAL STATIONS
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4 11.03 432 10
Stage-5 17.31 652 17
Stage-6 10.06 371 9
Total 66.56 2531 59

FOUNDATIONS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4 432 385 291 94 89.1% 9.76
Stage-5 652 650 480 170 99.7% 17.25
Stage-6 371 325 237 88 87.6% 8.65
Total 2531 2436 1854 582 96.2% 63.81

PIERS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4 432 383 289 94 88.7% 9.70
Stage-5 652 647 477 170 99.2% 17.15
Stage-6 371 267 180 87 72.0% 6.84
Total 2531 2373 1792 581 93.8% 61.85

SPAN ERECTION

Stage ERECTED Actual in VIADUCT Actual in STATION KMS
Stage-1 314 251 63 8.01
Stage-2 455 365 90 11.90
Stage-3 294 241 54 7.96
Stage-4 303 218 85 7.46
Stage-5 615 471 144 16.35
Stage-6 161 96 65 3.90
Total 2143 1642 501 55.59

SEGMENTS CAST

Casting Yard Casting Yard Name Scope No. Segment Cast Nos. Cast % KMs Complete
1 Uppal 16500 14772 89.53% 44.32
1 Qutubullahpur 8423 8423 100.00% 25.27
Total   24923 23195 93.07% 69.59