PROJECT UPDATES

Metro Project Updates

Construction Schedule (As on: 31-March-2018)

Corridor Number Corridor Details
Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

Projects Updates

STAGEWISE DETAILS

Stage TOTAL KMS TOTAL PIERS TOTAL STATIONS
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4# 11.47 440 10
Stage-5 17.31 652 17
Stage-6* 9.66 373 9
Total 66.60 2541 59

FOUNDATIONS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4# 440 393 299 94 89.3% 10.17
Stage-5 652 652 482 170 100.0% 17.31
Stage-6* 373 350 262 88 93.8% 9.01
Total 2541 2471 1889 582 97.2% 64.64

PIERS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4# 440 393 299 94 89.3% 10.17
Stage-5 652 652 482 170 100.0% 17.31
Stage-6* 373 341 254 87 91.4% 8.76
Total 2541 2462 1881 581 96.9% 64.39

SPAN ERECTION

Stage ERECTED Actual in VIADUCT Actual in STATION % Completed KMS
Stage-1 314 251 63 100.0% 8.01
Stage-2 455 365 90 100.0% 11.90
Stage-3 305 251 54 100.0% 8.25
Stage-4# 385 300 85 87.5% 9.97
Stage-5 651 498 153 99.8% 17.31
Stage-6* 281 198 83 75.6% 6.97
Total 2391 1863 528 94.1% 62.41

SEGMENTS CAST

Casting Yard Casting Yard Name Scope No. Segment Cast Nos. Cast %
1 Uppal 16500 15144 91.78%
2 Qutubullahpur 8423 8423 100.00%
  Total 24923 23567 94.56%