PROJECT UPDATES

Metro Project Updates

Construction Schedule (As on: 31-May-2018)

Corridor Number Corridor Details
Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

Projects Updates

STAGEWISE DETAILS

Stage TOTAL KMS TOTAL PIERS TOTAL STATIONS
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4# 11.47 440 10
Stage-5 17.31 652 17
Stage-6* 9.66 373 9
Total 66.60 2541 59

FOUNDATIONS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4# 440 396 300 96 90.0% 10.22
Stage-5 652 652 482 170 100.0% 17.31
Stage-6* 373 354 266 88 94.9% 9.13
Total 2541 2478 1894 584 97.5% 64.82

PIERS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4# 440 394 299 95 89.5% 10.18
Stage-5 652 652 482 170 100.0% 17.31
Stage-6* 373 349 262 87 93.6% 8.99
Total 2541 2471 1889 582 97.2% 64.64

SPAN ERECTION

Stage ERECTED Actual in VIADUCT Actual in STATION % Completed KMS
Stage-1 314 251 63 100.0% 8.01
Stage-2 455 365 90 100.0% 11.90
Stage-3 305 251 54 100.0% 8.25
Stage-4# 391 306 85 88.9% 10.14
Stage-5 651 498 153 99.8% 17.31
Stage-6* 312 228 84 83.9% 7.86
Total 2428 1899 529 95.6% 63.47

SEGMENTS CAST

Casting Yard Casting Yard Name Scope No. Segment Cast Nos. Cast %
1 Uppal 16500 15175 91.97%
2 Qutubullahpur 8423 8423 100.00%
  Total 24923 23598 94.68%